Saturday morning we went to a carpet store to see if they had something I liked at a reasonable price. They did! Floorman is coming out on Friday to measure. That afternoon Mom and I worked on putting some insulation in the dining room wall. When the window was out, Dad could see that there was none there. Mom cut an opening just under the window wide enough for me to wiggle the insulation through.
Dad worked on door moulding and transition strips between the hall and bedrooms.
Sunday, Dad finished installing door moulding and put up the floor moulding in the hall. That had been on hold until the door moulding was done. I got the ceiling trim for the master bedroom denailed, cleaned up, and painted. Mom patched up the hole from Saturday under the window.
We're getting there on the house. There should be an open house sometime this summer. Here's the still to do list (created Sunday afternoon):
- Ceiling trim: master, guest, & bedroom
- finish painting hallway doors (including linen closet)
- apply socket & switch plates
- kitchen tile
- living room window
- patio door
- texture & paint wall around dining room & patio door
- kitchen trim
- exterior paint
- roof
- blinds
- door knobs
- shower
- door jambs
- electric panel
- closet doors
No comments: